Construction Outline

At our meeting, Les explained the construction process in more detail, which was very helpful.  Basically Adair breaks it into 3 parts.

Phase 1 includes the foundation, framing, rough plumbing, roofing, and rough electrical.  He explained that this usually takes about 33 days.

next - there's the middle part - which includes drying out the house, inspections and utility connections.  Because these tasks are part of the home owner's responsibility, the time this takes is up to us and can vary substantially.

Finally - Phase 2 - which includes insulation, Sheetrock, painting, and finishing.  This takes about 45-55 days.

It was great to have him break it down like this.  I know that they aren't hard numbers, but it's nice to have a guess about when things will happen.

I'm totally ready to get going!