Tuesday, March 8, 2011

Update

Today we had our permit review meeting with the county.  Sandra from Adair was there and had all the information the county needed.  We applied for the building permit and the septic permit.  We also applied for an address, which should take a couple of weeks.

Turnaround time on the permits is about 4 weeks.

We should have the site prep done by then....

if it would ever stop raining...