A brief timeline of when things happened.
Items are linked to relevant posts.
June 6 - House dryout complete
June 2 - House Dryout Begins
May 15 - Underfloor plumbing and underfloor framing pass inspection.
May 6 - Foundation poured
April 30 - Foundation forms set
April 25 - Site inspection with Adiar
April 22 - Site prep complete, power & water hooked up
April 4 - Building permit approved
April 1 - Site prep started
April 1 - Address assigned
March 16 - Septic permit approved
March 8 - Applied for building and septic permits