Thursday, June 2, 2011

Phase One Complete!

We got a call from Adair on Tuesday...

They will be ready for us to start drying out the house out today!

Josh is renting a dehumidifier, fans and a heater.

The foundation was poured on May 6.  They told it would take 33 days to complete the foundation, framing, rough plumbing, and rough electrical.  The plumbing and electrical will be done early next week, so we're right on track.

what's next?

We're in charge of:
  • Site clean-up
  • permanent hook up of water, power and septic to the house
  • Drying out the house 
  • Rain drains and back filling
  • and, if the rain ever stops - painting and sealing the exterior.

Once the house is dry, they'll move on to Phase II - which starts with insulation and sheet rock. 

From the beginning of Phase II to Move In is between 45-50 days.  We're going to do our best to get our stuff done as quickly as possible!

It's all happening so quickly!